Question #1 Topic 1

When a process has proven itself to function at a Six Sigma level this means there are less than ________ defects per million opportunities.

  • A. 1.7
  • B. 2.6
  • C. 3.4
  • D. 10
Reveal Solution Hide Solution   Discussion  

Correct Answer: C 🗳️

Question #2 Topic 1

Six Sigma refers to a process whose output has at least 95% of its data points within 6 Standard Deviations from the Mean.

  • A. True
  • B. False
Reveal Solution Hide Solution   Discussion  

Correct Answer: B 🗳️

Question #3 Topic 1

Training cost is $3,000 and a project required an initial investment of $12,000. If the project yields monthly savings of $1,800 beginning after 3 months, what is the payback period in months (before money costs and taxes)?

  • A. 4.17
  • B. 8.33
  • C. 11.33
  • D. 28.28
Reveal Solution Hide Solution   Discussion   2

Correct Answer: C 🗳️

Question #4 Topic 1

The ROI for a project is a measurement metric that stands for Return on Investment and is one of the methods used to measure the success of a Lean Six Sigma project.

  • A. True
  • B. False
Reveal Solution Hide Solution   Discussion  

Correct Answer: A 🗳️

Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...