When many Scrum Teams are working on the same product, should all of their Increments be integrated every Sprint?
Correct Answer:
B
🗳️
When can a Development Team cancel a Sprint?
Correct Answer:
A
🗳️
Reference:
https://scrumguides.org/scrum-guide.html#:~:text=A%20Sprint%20could%20be%20cancelled,authority%20to%20cancel%20the%20Sprint
Which output from Sprint Planning provides the Development Team with a target and overarching direction for the Sprint?
Correct Answer:
B
🗳️
Reference:
https://www.scrum.org/forum/scrum-forum/5606/sprint-planning#:~:text=A%20Sprint%20Goal%20should%20set,of%20a%20Sprint%20Planning%
20session
How should a Development Team deal with non-functional requirements?
Correct Answer:
A
🗳️
When is a Sprint over?
Correct Answer:
D
🗳️
Reference:
https://www.extremeuncertainty.com/in-scrum-when-is-a-sprint-over/#:~:text=The%20short%20and%20simple%20answer,%2C%20one%20week%2C
%20etc