Question #1 Topic 1

Which Scrum artifacts provide transparency and opportunities for inspection and adaptation?

  • A. Burndown Charts, release plan and Product Backlog
  • B. Sprint Backlog, Product Backlog and Increment
  • C. Definition of Done and Product Backlog
  • D. Definition of Done, Sprint Backlog and Product Backlog
Reveal Solution Hide Solution   Discussion  

Correct Answer: B 🗳️

Question #2 Topic 1

Taylor, a Scrum Master, was asked for their advice on how large a Scrum Team should be. Which of these responses is correct?

  • A. "The typical size of an effective Scrum Team is ten or fewer."
  • B. "Size doesn't matter as long as the Scrum Master coordinates the work in collaboration with the Product Owner."
  • C. "Bigger teams communicate better, are more productive and produce better results."
  • D. "When a team expands beyond ten, activities, like verification and operations, are assigned to a different team."
Reveal Solution Hide Solution   Discussion  

Correct Answer: A 🗳️

Question #3 Topic 1

What is one service a Scrum Master provides to the Product Owner?

  • A. Assign tasks to the Developers
  • B. Write user stories
  • C. Prioritize the backlog
  • D. Find effective Product Backlog management techniques
Reveal Solution Hide Solution   Discussion  

Correct Answer: D 🗳️

Question #4 Topic 1

What is the purpose of the Sprint Retrospective?

  • A. Inspect how the last Sprint went with regards to individuals, interactions, processes, tools and Definition of Done
  • B. Plan the incomplete work for the next Sprint and submit reasons to the Product Owner
  • C. Explain what Backlog items have been done and what has not been done
  • D. Identify Developers who did not perform well in the Sprint
Reveal Solution Hide Solution   Discussion  

Correct Answer: A 🗳️

file Viewing page 1 out of 13 pages.
Viewing questions 1-4 out of 50 questions
Next Questions
Browse atleast 50% to increase passing rate cup
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago