Which statements are correct for standard processes in PM/PS cost control? (Choose two.)

  • A. Budget can be assigned to a maintenance plan
  • B. Budget can be assigned to a WBS element
  • C. Maintenance order costs can be settled to a WBS element
  • D. Maintenance costs can be settled to a network operation
Reveal Solution Hide Solution   Discussion  

Correct Answer: BD 🗳️

Question #2 Topic 1

Which of the following objects can you directly assign when you define the work center? (Choose two.)

  • A. Calculation key
  • B. Fixed price of the activity type
  • C. Capacity category
  • D. Organizational unit (HR)
Reveal Solution Hide Solution   Discussion  

Correct Answer: CD 🗳️

Question #3 Topic 1

Which of the following are components of cloud-based SAP Intelligent Asset Management? (Choose two.)

  • A. Worker safety applications
  • B. SAP Work Manager
  • C. SAP Predictive Maintenance and Service
  • D. SAP Asset Manager
Reveal Solution Hide Solution   Discussion  

Correct Answer: CD 🗳️

Question #4 Topic 1

What is the correct receiver object type for the settlement of a refurbishment order?

  • A. The cost center
  • B. The fixed asset
  • C. The WBS element
  • D. The material
Reveal Solution Hide Solution   Discussion  

Correct Answer: D 🗳️

Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...