Topic 1 - Topic 1, Agile Project Delivery

Question #1 Topic 1

What criterion does the Product Owner use to sequence the Product Backlog?

  • A. Resource availability
  • B. Business priority
  • C. Relative effort
  • D. Complexity
Reveal Solution Hide Solution   Discussion  

Correct Answer: B 🗳️

Question #2 Topic 1

What is the purpose of the Scrum Board?

  • A. To visualize team progress
  • B. To manage the resource load
  • C. To document the results of the Integration Test
  • D. To show the functional breakdown of the solution scope
Reveal Solution Hide Solution   Discussion  

Correct Answer: A 🗳️

Question #3 Topic 1

What is the key characteristic of the Agile project approach?

  • A. Formal and detailed documentation
  • B. Frequent and detailed project scheduling
  • C. Frequent Quality Gates
  • D. Iterative build with frequent inspections
Reveal Solution Hide Solution   Discussion  

Correct Answer: D 🗳️

Question #4 Topic 1

According to the Definition of Done, which activity must be completed for each Sprint?

  • A. Functionality must be tested in the Production System (PROD)
  • B. The solution must be built and configured in the development system (DEV)
  • C. Functionality must be released to the business
  • D. End-user training must be delivered
Reveal Solution Hide Solution   Discussion  

Correct Answer: B 🗳️

Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...