iSQI IREB-IT-CQ03 Exam Actual Questions

The questions for IREB-IT-CQ03 were last updated on Sept. 30, 2024.
  • Viewing page 1 out of 12 pages.
  • Viewing questions 1-4 out of 45 questions

Topic 1 - Exam A

Question #1 Topic 1

You are project manager for a system that your company is creating for the military in the field of logistics. A requirements engineer has been assigned to your project but does not have all the desirable skills for this role. In respect to the attributes of the requirements engineer, which of the following statements implies the greatest risk for the requirements engineering?

  • A. The requirements engineer is not familiar with the military ranks and so cannot deal adequately with the hierarchical sensitivities.
  • B. The requirements engineer does not have detailed knowledge of the military norms and standards that should be applied to the system.
  • C. The requirements engineer has no solid project management training.
  • D. The requirements engineer is introverted and has no knowledge of requirements elicitation and documentation.
Reveal Solution Hide Solution   Discussion  

Correct Answer: D 🗳️

Question #2 Topic 1

Which of the following statements best characterizes the relationship between a requirements engineer and a stakeholder in the role of a tester?

  • A. The requirements engineer delivers input for the work of the stakeholder.
  • B. The output from the requirements engineer is managed by the stakeholder.
  • C. The stakeholder delivers input for the requirements engineer.
  • D. The stakeholder monitors the work of the requirements engineer.
  • E. The work of the requirements engineer is not related to the role of the stakeholder.
Reveal Solution Hide Solution   Discussion  

Correct Answer: A 🗳️

Question #3 Topic 1

Which sentence best characterizes the term "stakeholder"?

  • A. The external actors interacting with a system and the technical interfaces to surrounding systems are designated as stakeholders.
  • B. Stakeholders are persons and organizations affected by the development and the use of the system or of the product.
  • C. Stakeholders are special interest representatives who are responsible for the approval of the first project phase.
  • D. A stakeholder is responsible for the administration of the software development environment.
Reveal Solution Hide Solution   Discussion  

Correct Answer: B 🗳️

Question #4 Topic 1

You are assigned to carry out and document a system and context delimitation for a software system that is to be developed.
What diagram is least suited for the representation of the delimitation?

  • A. Class diagram
  • B. Use case diagram
  • C. Statediagram
  • D. Context diagram with data flows
Reveal Solution Hide Solution   Discussion  

Correct Answer: C 🗳️

Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...