PK0-005 Actual Exam Questions

Last updated on Jan. 22, 2025.
Vendor:CompTIA
Exam Code:PK0-005
Exam Name:CompTIA Project+
Exam Questions:317
 

Topic 1 - Exam A

Question #1 Topic 1

DRAG DROP -
During a gate review meeting, the deliverable was rejected by the customer.
Review the dashboard.
Part 1: Drag and drop each task, placing them in the correct order based on the project change control process.
Part 2: Select the proper document(s) to be updated.

Reveal Solution Hide Solution   Discussion   8

Correct Answer:

Question #2 Topic 1

A PM is responsible for implementing a new customer relationship management system and has learned that the sales organization is reluctant to utilize the new system. The organization’s reluctance could jeopardize the success of the project. Which of the following steps should be taken to understand the adoption issues and gain organizational acceptance of the initiative? (Choose two.)

  • A. Train users on the proper use of the system.
  • B. Escalate the issue to the CCB.
  • C. Hold sessions to understand user challenges.
  • D. Track system usage and report user activity.
  • E. Log the issue in the project risk register.
  • F. Create a memorandum of acceptable use.
Reveal Solution Hide Solution   Discussion   12

Correct Answer: AC 🗳️

Question #3 Topic 1

Following a successful release, a project manager sent a survey to all stakeholders to gain an understanding of opportunity areas for the team. Which of the following can use the survey results as an input?

  • A. Daily stand-up
  • B. Project momentum
  • C. Performance feedback
  • D. Meeting minutes
Reveal Solution Hide Solution   Discussion   10

Correct Answer: C 🗳️

Question #4 Topic 1

Which of the following is an activity that should be used in the closing phase of a project to support the project triple constraint?

  • A. Evaluating the project
  • B. Releasing the resources
  • C. Closing the contracts
  • D. Reconciling the budget
Reveal Solution Hide Solution   Discussion   13

Correct Answer: D 🗳️

Question #5 Topic 1

During a quality analysis review, the causes of several issues have been highlighted. Which of the following should the project manager use to identify the MOST important causes?

  • A. Ishikawa diagram
  • B. Scatter diagram
  • C. Pareto chart
  • D. Decision tree
Reveal Solution Hide Solution   Discussion   5

Correct Answer: C 🗳️

Question #6 Topic 1

Which of the following BEST describes how an organization should coordinate management of multiple related projects?

  • A. Apply the SDLC process.
  • B. Establish a program.
  • C. Consult the CCB.
  • D. Use different frameworks.
Reveal Solution Hide Solution   Discussion   4

Correct Answer: B 🗳️

Question #7 Topic 1

A project team gathers weekly to review its progress. Which of the following is the project manager MOST likely to have prepared to ensure team members who are absent remain informed about assignments?

  • A. Status report
  • B. Project plan
  • C. Change log
  • D. Meeting minutes
Reveal Solution Hide Solution   Discussion   5

Correct Answer: D 🗳️

Question #8 Topic 1

A project manager prefers to have immediate contact with team members because it allows for faster response times and more interactive discussions. Which of the following communication methods should the project manager use?

  • A. Synchronous
  • B. Informal
  • C. Asynchronous
  • D. Formal
Reveal Solution Hide Solution   Discussion   2

Correct Answer: A 🗳️

Question #9 Topic 1

As part of the planning phase, a PM has defined tasks, durations, resources, and costs. Which of the following is the NEXT step in the process?

  • A. Update the work breakdown structure.
  • B. Review the backlog.
  • C. Seek baseline approval.
  • D. Establish the resource pool.
Reveal Solution Hide Solution   Discussion   2

Correct Answer: C 🗳️

Question #10 Topic 1

A project manager realizes that a project will not be completed on time due to resource constraints. Which of the following actions should the project manager take NEXT?

  • A. Trigger the contingency plan and communicate with the stakeholders.
  • B. Work with the functional managers to create a work-around.
  • C. Submit a change request to the change control board.
  • D. Transfer the risk by hiring a new vendor who was successful on a previous project.
  • E. Set up an escalation meeting with the sponsor.
Reveal Solution Hide Solution   Discussion   9

Correct Answer: C 🗳️

file Viewing page 1 out of 32 pages.
Viewing questions 1-10 out of 317 questions
Next Questions
Browse atleast 50% to increase passing rate cup
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago