A project manager is attempting to establish the proper sequencing and duration of project activities.
Which of the following would be the MOST beneficial?
Correct Answer:
A
🗳️
Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 160
Which of the following are characteristics of a project? (Choose two.)
Correct Answer:
BC
🗳️
Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 27
A company has determined it does not have the in-house capability to perform a project and wants to procure third-party services.
Which of the following documents will the company MOST likely release FIRST?
Correct Answer:
B
🗳️
Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 300
The project manager was asked to provide recommendations for the removal of a vendor. A meeting was scheduled with the key stakeholders and the project sponsor to highlight the reasons for this recommendation.
Which of the following should the project manager bring to the meeting to support this recommendation? (Choose two.)
Correct Answer:
AE
🗳️
Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 291, p. 327
A project manager is creating the WBS.
In which of the following phases is the project?
Correct Answer:
B
🗳️
Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 139
Which of the following is a characteristics of a matrix organization?
Correct Answer:
D
🗳️
Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 56
A WBS is being developed for a project.
Which of the following would be BEST suited to contribute cost and time estimates for the project activities?
Correct Answer:
A
🗳️
A project manager is assigned to a project and has not had a handover meeting with the previous project manager. The new project manager is reviewing the percent of project completion, schedule progress, and budget constraints.
Which of the following documents should the project manager use to obtain this information?
Correct Answer:
D
🗳️
Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 328
A stakeholder is unaware of a project's status.
Which of the following documents should the project manager consult to ensure all stakeholders are notified of project changes? (Choose two.)
Correct Answer:
AD
🗳️
Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 261
There are four parallel paths on a network diagram. The summary duration of each path is below:
A, C, G: 10 weeks -
A, B, F: 8 weeks -
D, E, H: 12 weeks -
D, B, F: 7 weeks -
Which of the following tasks are on the critical path?
Correct Answer:
C
🗳️
Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 175