Question #1 Topic 1

Which of the following methods would be a valid approach for capturing process execution errors? (Select 3)

  • A. Calling an external program to send SNMP traps.
  • B. Logging to event log and collecting via an external tool.
  • C. Selecting "send to external monitoring tool" from the Blue Prism process designer.
  • D. Generating emails from the process.
Reveal Solution Hide Solution   Discussion  

Correct Answer: ABD 🗳️

Question #2 Topic 1

What must be considered before operating multiple Runtime Resources on a single Windows desktop? (Select 1)

  • A. There are no conditions, only one Runtime Resource can be set to listen per Windows session.
  • B. Each Runtime Resource must listen on a different port and the processes which run on the device must not impact other processes on the same device.
  • C. Each Runtime Resource must listen on the same port and the processes which run on the device must not impact other processes on the same device.
  • D. Each Runtime Resource must listen on a different port.
Reveal Solution Hide Solution   Discussion  

Correct Answer: B 🗳️

Question #3 Topic 1

What restrictions should be considered if using XenDesktop for delivery of the Runtime Resources? (Select 2)

  • A. Login Agent must be used to initiate the login to the device vs the Citrix Client.
  • B. Only version 5 of Blue Prism is supported with XenDesktop.
  • C. Login Agent is only supported from version 7.6 of XenDesktop, due torestrictions on 3rd party credential provider support prior to this.
  • D. XenDesktop is not a supported platform for the Runtime Resource.
  • E. Surface Automation will need to be used for all automations.
Reveal Solution Hide Solution   Discussion  

Correct Answer: AC 🗳️

Question #4 Topic 1

What should be considered when configuring high availability and disaster recovery scenarios for availability of Business Processes managed by Blue Prism?
(Select 2)

  • A. Resource pools and Active Queues can be used to distribute work to Runtime Resources which are online
  • B. The Runtime Resources are "stateful" devices, therefore any failure or maintenance event should also be taken into account in the process design and scheduling methodology
  • C. Using a load balancer and 2 application servers will ensure high availability of an automated process
  • D. Use the setting within a Blue Prism Process to force a process to fail over to an alternative Runtime Resource in the event of a failure.
Reveal Solution Hide Solution   Discussion  

Correct Answer: AC 🗳️

file Viewing page 1 out of 12 pages.
Viewing questions 1-4 out of 45 questions
Next Questions
Browse atleast 50% to increase passing rate cup
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago