Question #: 45
Topic #: 1
[All 3V0-21.21 Questions]

In a meeting to discuss the minimum viable product (MVP) deployment of a new customer-facing application, the key stakeholder shares details of the application components and the application administrators share details of performance and integrity tests for the application.
The application will be made up of the following components:

A web server -

- Steps to confirm the web server is operating correctly will take 15 minutes after the application server is online.
✑ An application server
- Steps to confirm application server integrity will take 15 minutes after the database is online.
✑ A database server
- The database server will be managed by a database administrator, with an agreed service-level agreement (SLA) to restore and validate database services within one hour.
The existing VMware infrastructure offers a recovery point objective (RPO) of 5 minutes and recovery time objective (RTO) of 15 minutes through a combination of backups and replication.
In the event of an outage impacting all three application components, how long will it take for the application to recover and complete all checks?

  • A. 15 minutes
  • B. 60 minutes
  • C. 105 minutes
  • D. 90 minutes
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
zqd
Highly Voted 2 years ago
Selected Answer: C
C- 105 : 15 minutes RTO to restore VMs, +60 for Database Admin to restore/validate DB services + 15 minutes for Application server integrity checks and 15 more minutes for web server.
upvoted 7 times
...
VCIX
Highly Voted 2 years, 2 months ago
C - 1 hr for database, 15 mins for each of the other 2 servers = 90 mins then + 15 min RTO = 105 mins
upvoted 5 times
...
FR_Wolfman
Most Recent 10 months, 1 week ago
Selected Answer: C
I would say D. It is stated we have an outage impacting the 3 application components, not the VMware infrastructure. So we have only the 3 servers to restore and make available --> 90 minutes (1 hours for DB, and 15min for each of the other servers).
upvoted 1 times
...
ghostmdb
11 months, 1 week ago
DB admin takes 60 minutes to RESTORE and validate database services. So RTO of 15 minutes is inside that 60 minutes. During that 60 minutes, the other 2 services can be restored, so RTO of 15 minutes would not impact. So the last delay will be the validating of App Server and Web Server, 15 + 15 So 60 + 15 + 15 = 90
upvoted 1 times
...
diegof1
1 year, 10 months ago
Selected Answer: C
DataBase Server (60 min) + App Server (15 min) + Web Server (15 min) + RTO (15 min) = 105 min
upvoted 1 times
...
taku94
2 years, 1 month ago
1hr (60min) for Database to recover Application Server 15 min after Database recovery WebServer 15min after application server recovery If so, 60 + 15Min + 15Min = 90min?
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...