Following the deployment of a new all-flash vSAN 7.0 U1 stretched cluster, an administrator has been tasked with decommissioning the existing hybrid vSAN 6.7 U3 stretched cluster since the hardware is becoming end-of-life. In addition to Virtual Machine storage, the hybrid vSAN cluster also provides iSCSI target services.
The administrator has completed the following tasks:
• All workloads have been successfully migrated to the new vSAN stretched cluster.
• The iSCSI target service has been enabled on the new vSAN stretched cluster.
Which three additional tasks should the administrator complete to properly decommission the hybrid vSAN stretched cluster and ensure that all data is removed? (Choose three.)