A Scrum Team wants to conduct a meeting in which they plan to deliberate on ways to improve team collaboration and effectiveness in future. This can be identified as which type of meeting?
C, SBOK page 258 - 112.2.2.1 Retrospect Project Meeting - The Retrospect Project Meeting is a meeting to determine ways in which team collaboration and
effectiveness can be improved in future projects.