Exam Scrum Master Certified topic 1 question 81 discussion

Actual exam question from Vmedu's Scrum Master Certified
Question #: 81
Topic #: 1
[All Scrum Master Certified Questions]

A Scrum Team wants to conduct a meeting in which they plan to deliberate on ways to improve team collaboration and effectiveness in future. This can be identified as which type of meeting?

  • A. Sprint Planning meeting.
  • B. Review Sprint meeting.
  • C. Retrospect Project meeting.
  • D. Review Project meeting.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️
Reference:
https://thedigitalprojectmanager.com/sprint-planning-meeting/

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Jozef_joe
1 year, 3 months ago
C, SBOK page 258 - 112.2.2.1 Retrospect Project Meeting - The Retrospect Project Meeting is a meeting to determine ways in which team collaboration and effectiveness can be improved in future projects.
upvoted 1 times
...
bovos
3 years ago
answer: C
upvoted 2 times
...
skrzek
3 years, 4 months ago
Answer: C
upvoted 4 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.