A project on developing quality testing equipment for an agro-based industry will start with the Create Deliverables process. Which of the following are NOT inputs to the current process?

A) Scrum Core Team -

B) Acceptance Criteria -

C) Impediment log -

D) Length of Sprint -

  • A. A and Ð’
  • B. B and D
  • C. A and C
  • D. Ð’ and C
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️
Reference:
https://katherinemichel.gitbooks.io/agile-sprint-playbook/project-management/scrum-body-of-knowledge-phases.html

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
ekmode
3 years, 11 months ago
Answer: B SBOK GUIDE - 10.1 Create Deliverables INPUTS ARE 1. Scrum Core Team* 2. Sprint Backlog* 3. Scrumboard* 4. Impediment Log*
upvoted 3 times
patricpotter1992
3 years, 4 months ago
Definitely B. Thank you.
upvoted 1 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...