Question #: 55
Topic #: 1
[All Scrum Master Certified Questions]

Listed below are some risks and issues that might be encountered during the course of a project. Identify which of the following are risks (not issues).
A) After extensive training, marketing representatives might still not be ready to take orders after the project is launched.
B) The painting crew might be delayed due to heavy rain, which could negatively impact the project schedule.
C) Funding was not approved.
D) Requirements, as currently defined, are unclear.

  • A. Only Ð’
  • B. A and C
  • C. Ð’ and D
  • D. A and B
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
ekmode
Highly Voted 3 years, 11 months ago
Answer: D , SBOK GUIDE -7.3.1-Difference between Risks and Issues- REF EXAMPLE
upvoted 5 times
...
bovos
Most Recent 3 years ago
A and B=risks C and D=Issues
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...