Question #: 32
Topic #: 1
[All Scrum Master Certified Questions]

Scrum Masters have to solve both internal and external impediments for the Scrum team during the Create Deliverables process. To do so, they record the impediments in the Impediment Log during _________________________.
A) Daily Standup Meetings.
B) Sprint Review Meetings.
C) Release Planning Meetings.
D) Sprint Planning Meetings.

  • A. A and Ð’
  • B. A
  • C. A and D
  • D. A, B, and C
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️
Reference:
http://www.cs.vsu.ru/~svv/spm/SBOK_Guide_3rd_edition_English_Sample.pdf
(45)

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
DTM070
2 years, 11 months ago
Answer is A & B
upvoted 3 times
...
ekmode
3 years, 11 months ago
Answer: A, SBOK GUIDE-10.1.1.14-Impediment Log* Impediments should be formally recorded by the Scrum Master in an Impediment Log, and can be discussed during Daily Standup Meetings and Sprint Review Meetings as appropriate.
upvoted 4 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...