Exam Scrum Master Certified topic 1 question 38 discussion

Actual exam question from Vmedu's Scrum Master Certified
Question #: 38
Topic #: 1
[All Scrum Master Certified Questions]

During a Scrum of Scrums Meeting certain questions are answered. Which of the following are the questions answered?
A) What has my team been working on since the last meeting?
B) What will my team do until the next meeting?
C) What were other teams counting on our team to finish that remains undone?
D) What is our team planning on doing that might affect other teams?

  • A. C and D.
  • B. A and Ð’
  • C. Ð, B, and D.
  • D. All of the above.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Reference:
http://www.cs.vsu.ru/~svv/spm/SBOK_Guide_3rd_edition_English_Sample.pdf
(59)

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
ekmode
Highly Voted 4 years ago
Answer : D - As per SBOK Guide - Four specific questions. 1) What has my team been working on since the last meeting? 2) What will my team do until the next meeting? 3) What were other teams counting on our team to finish that remains undone? 4) What is our team planning on doing that might affect other teams?
upvoted 6 times
...
scrummastercertification09
Most Recent 1 month, 1 week ago
Answer: D. All of the above. In a Scrum of Scrums meeting, teams typically discuss all these aspects to ensure alignment and collaboration across multiple teams. Each question helps to clarify progress, upcoming work, and dependencies, fostering transparency and coordination among teams. For anyone looking to enhance their understanding of these dynamics, obtaining a Scrum Master certification can provide valuable insights and frameworks.
upvoted 1 times
...
Mi_Windsor
1 year, 5 months ago
The correct answer id D
upvoted 1 times
...
CharloPc
1 year, 6 months ago
Some of the answers like this answer for this question is not correct. The answer is D which is expressly stated in SBOG 4th Edition page 292
upvoted 1 times
...
Subarashi
1 year, 6 months ago
Answer: D. SBOK Guide 13.3.5
upvoted 1 times
...
rthakkar
1 year, 11 months ago
Selected Answer: D
As per SBOK Guide - Four specific questions. 1) What has my team been working on since the last meeting? 2) What will my team do until the next meeting? 3) What were other teams counting on our team to finish that remains undone? 4) What is our team planning on doing that might affect other teams?
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago