exam questions

Exam Scrum Master Certified All Questions

View all questions & answers for the Scrum Master Certified exam

Exam Scrum Master Certified topic 1 question 2 discussion

Actual exam question from Vmedu's Scrum Master Certified
Question #: 2
Topic #: 1
[All Scrum Master Certified Questions]

A town has begun a project that involves keeping track of the buses traveling on the roads of the town. Which of the following is NOT a characteristic of this project if it is managed according to Scrum Framework?

  • A. Detailed upfront planning will be done to ensure that risks are identified early on.
  • B. The team working on this project will meet every day for 15 minutes to list impediments to completing their tasks.
  • C. The Product Owner will prioritize the tasks that deliver maximum business value.
  • D. The customer does not have to be able to define very concrete requirements early on.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
asbok
Highly Voted 4 years ago
A. Page 133 of SBOK Guide 7.8 Scrum vs. Traditional Project Management
upvoted 8 times
...
ekmode
Highly Voted 3 years, 11 months ago
Answer :A
upvoted 6 times
...
558c08a
Most Recent 2 months, 1 week ago
Correct answer A. Detailed upfront planning is aligned with traditional project manajement.
upvoted 1 times
...
bexofe7031
8 months, 3 weeks ago
correct answer is A https://bitly.ws/3fSRY
upvoted 2 times
...
e72ac02
8 months, 4 weeks ago
B is the correct Pg 134 SBOK Guide
upvoted 1 times
...
Mi_Windsor
1 year, 4 months ago
Answer is A and the planning and risk are done in early phases such as in Waterfall
upvoted 1 times
...
mnlferreiro
2 years ago
Selected Answer: A
correct answer is A
upvoted 1 times
...
abivij
2 years, 7 months ago
Selected Answer: A
In Traditional project management models, there is emphasis on detailed upfront planning to identify, assess, and determine risk responses for all project risks.
upvoted 1 times
...
StephanJo
2 years, 7 months ago
Selected Answer: A
Answer :A
upvoted 2 times
...
patricpotter1992
3 years, 4 months ago
Answer: A
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...