Suggested Answer:B🗳️
Velocity measures how many user stories were completed by the team, on average, in previous sprints. It assists in estimating how much work the team is able to accomplish in future sprints. Reference: https://www.sealights.io/software-development-metrics/11-scrum-metrics-and-their-value-to-scrum-teams/
B, SBOK 11.2.2.4 Metrics and Measuring Techniques - Team velocity—Number of story points done in a given Sprint