An administrator configures a default Standard file system backup policy, which backs up very large file systems from a set of clients. There are multiple scheduled backup attempts configured.
How can the administrator reduce the amount of time needed to complete these backup jobs after failures?

  • A. configure the Take checkpoints every policy setting
  • B. increase the Job retry delay host property setting
  • C. use the Resume Job action instead of Restart Job
  • D. increase the Client connect timeout host property setting
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
fmatzinger
3 years, 9 months ago
I think answer A is correct because backups would resume from last checkpoint thus not from the beginning answer B would help to relaunch quickly, but from the beginning
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago