A power outage on Site A is expected during the night. The disaster recovery strategy has been implemented (see diagram). What is the correct way to start replicated VMs on Site B to minimize data loss?
A - Permanently changes the source to a replica.
B - Use when you manually initiate the change, generally when you know there will be a problem and act preventatively.
C - It seems to be ideal, since everything happened overnight.
D - When you have a plan.
B.
Planned failover is helpful when you know that your primary VMs are about to go offline and you need to proactively switch the workload from original VMs to their replicas.
https://helpcenter.veeam.com/archive/backup/110/vsphere/planned_failover.html
upvoted 2 times
...
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
debloid
8 months agodebloid
8 months agojack98
11 months agoa0e9076
1 year ago_zero
1 year agoR3dd1e
1 year, 1 month agoatinivelli
1 year, 2 months agopepe_uchiha
1 year, 4 months agorb2026494
1 year, 4 months ago