Question #: 125
Topic #: 1
[All UiADPv1 Questions]

“Process A” is scheduled to run at 2:00 PM using a time trigger with the Schedule ending of job execution feature configured to stop the job after 20 minutes. Assuming that the robots are busy and “Process A” is queued until 2:05 PM, at what time will “Process A” be stopped?

  • A. 2:20 PM
  • B. 2:25 PM
  • C. 2:05 PM
  • D. 2:28 PM
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Sanjib40
2 months, 4 weeks ago
It should be 2:20 PM
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.