Question #: 258
Topic #: 1
[All OG0-091 Questions]

In which ADM phase does the value and change management process determine the circumstances under which the Architecture Development Cycle will be initiated to develop a new architecture?

  • A. Phase H
  • B. Phase F
  • C. Phase E
  • D. Preliminary Phase
  • E. Phase G
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
rockyslav
2 years, 1 month ago
15.3.7 Activate the Process to Implement Change Activate the architecture process to implement change: ■ Produce a new Request for Architecture Work and request for investment ■ Ensure any changes implemented in this phase are captured and documented in the Architecture Repository 15.4 Outputs The outputs of Phase H may include, but are not restricted to: ■ Architecture updates (for maintenance changes) ■ Changes to architecture framework and principles (for maintenance changes). In Phase H it is critical that the governance body establish criteria to judge whether a Change Request warrants *just an architecture update* or whether it *warrants starting a new cycle of the Architecture Development Method* (ADM).
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...