Which of the following terms is defined as the key interests that are crucially important to the stakeholders in a system?

  • A. Viewpoints
  • B. Concerns
  • C. Requirements
  • D. Principles
  • E. Views
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
rockyslav
2 years, 1 month ago
https://pubs.opengroup.org/architecture/togaf9-doc/arch/chap31.html - "Concerns" are interests in a system relevant to one or more of its stakeholders. Concerns may pertain to any aspect of the system's functioning, development, or operation, including considerations such as performance, reliability, security, distribution, and evolvability and may determine the acceptability of the system. - An "architecture view" is a representation of a system from the perspective of a related set of concerns. It consists of one or more architecture models of the system. - "Stakeholders" are individuals, teams, organizations, or classes thereof, having an interest in a system.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...