Question #: 144
Topic #: 1
[All OG0-091 Questions]

Which ADM phase provides architectural oversight of the implementation?

  • A. Preliminary Phase
  • B. Phase A
  • C. Phase E
  • D. Phase G
  • E. Phase H
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Teringzooi
8 months, 1 week ago
Selected Answer: D
Correct answer: D - Phase G https://pubs.opengroup.org/architecture/togaf9-doc/arch/chap14.html
upvoted 1 times
...
1learner
1 year ago
Phase G: Implementation Governance This chapter provides an architectural oversight of the implementation.
upvoted 1 times
...
rockyslav
2 years, 1 month ago
The objectives of Phase G are to: 1. "Ensure conformance with the Target Architecture" by implementation projects. 2. "Perform appropriate Architecture Governance" functions for the solution and any implementation-driven architecture Change Requests. This Phase provides an architectural oversight of the implementation. Phase G establishes the connection between architecture and implementation organization, through the Architecture Contract.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...