What document is sent from the sponsoring organization to the architecture organization to trigger the start of an ADM cycle?

  • A. Architecture Contract
  • B. Architecture Definition Document
  • C. Architecture Vision
  • D. Request for Architecture Work
  • E. Statement of Architecture Work
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Teringzooi
8 months, 2 weeks ago
Selected Answer: D
Correct answer: D https://pubs.opengroup.org/architecture/togaf90-doc/epf/TOGAF9/workproducts/Request%20for%20Architecture%20Work_6F6E672A.html
upvoted 1 times
...
1learner
1 year, 1 month ago
32.2.17 Request for Architecture Work Purpose This is a document that is sent from the sponsoring organization to the architecture organization to trigger the start of an architecture development cycle. Requests for Architecture Work can be created as an output of the Preliminary Phase, a result of approved architecture Change Requests, or terms of reference for architecture work originating from migration planning. In general, all the information in this document should be at a high level.
upvoted 1 times
...
JITPATIL
1 year, 7 months ago
D Request for Architecture Work
upvoted 1 times
...
rockyslav
2 years, 1 month ago
32.2.17 Request for Architecture Work Purpose This is a document that is sent from the sponsoring organization to the architecture organization to trigger the start of an architecture development cycle. Requests for Architecture Work can be created as an output of the Preliminary Phase, a result of approved architecture Change Requests, or terms of reference for architecture work originating from migration planning. In general, all the information in this document should be at a high level.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...