Answer is B: B. It highlights the impacts of change
The basic premise is to highlight a shortfall between the Baseline Architecture and the Target Architecture; that is, items that have been deliberately omitted, accidentally left out, or not yet defined.
https://pubs.opengroup.org/architecture/togaf9-doc/arch/chap23.html
The technique known as Gap Analysis is widely used in the ADM to validate an architecture that is being developed. The basic premise is to highlight a shortfall between the Baseline Architecture and the Target Architecture; that is, items that have been deliberately omitted, accidentally left out, or not yet defined.
- A key step in validating an architecture is to consider what may have been forgotten.
- The most critical source of gaps that should be considered.
- The gap analysis technique should be used in *Phases B, C, D, and E of the ADM*.
upvoted 2 times
...
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
kashifwasee
2 weeks, 3 days agoaleneosp
1 month, 3 weeks agoSubscriberHK
7 months, 3 weeks agoawsboyX
9 months, 1 week agoTeringzooi
1 year agoMohammad_Mel
1 year, 8 months agorockyslav
2 years, 5 months agorockyslav
2 years, 5 months ago