Question #: 62
Topic #: 1
[All OG0-091 Questions]

Which phase of the ADM is an on-going activity that is visited throughout a TOGAF architecture project?

  • A. Architecture Change Management
  • B. Implementation governance
  • C. Migration planning
  • D. Preliminary Phase
  • E. Requirements Management
Show Suggested Answer Hide Answer
Suggested Answer: E 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
trato
11 months, 2 weeks ago
Correct answer is A. Architecture Change Management is an ongoing activity that spans multiple phases of the Architecture Development Method (ADM).
upvoted 1 times
...
rockyslav
2 years, 1 month ago
The objectives of the Requirements Management phase are to: Ensure that the Requirements Management process is sustained and operates for all relevant ADM phases. Manage architecture requirements identified during any execution of the ADM cycle or a phase. Ensure that relevant architecture requirements are available for use by each phase as the phase is executed. As indicated by the "Requirements Management" circle at the center of the ADM graphic, the ADM is continuously driven by the Requirements Management process. It is important to note that the Requirements Management circle denotes not a static set of requirements, but a dynamic process whereby requirements for Enterprise Architecture and subsequent changes to those requirements are identified, stored, and fed into and out of the relevant ADM phases, and also between cycles of the ADM.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...