Complete the sentence. During the implementation of an architecture, if the original Architecture Definition and requirements are not suitable, a ____ may be submitted to initiate further architecture work.
Typical contents of a Change Request are:
Description of the proposed change
Rationale for the proposed change
Impact assessment of the proposed change, including:
- Reference to specific requirements
- Stakeholder priority of the requirements to date
- Phases to be revisited
- Phase to lead on requirements prioritization
- Results of phase investigations and revised priorities
Recommendations on management of requirements
Repository reference number
Yes. Change Request.
https://pubs.opengroup.org/architecture/togaf9-doc/arch/chap32.html
32.2.11 Change Request
Purpose
During implementation of an architecture, as more facts become known, it is possible that the original Architecture Definition and requirements are not suitable or are not sufficient to complete the implementation of a solution. In these circumstances, it is necessary for implementation projects to either deviate from the suggested architectural approach or to request scope extensions. Additionally, external factors - such as market factors, changes in business strategy, and new technology opportunities - may open up opportunities to extend and refine the architecture.
In these circumstances, a Change Request may be submitted in order to kick-start a further cycle of architecture work.
During implementation of an architecture, as more facts become known, it is possible that the original architecture definition and requirements are not suitable or are not sufficient to complete the implementation of a solution. In these circumstances, it is necessary for implementation projects to either deviate from the suggested architectural approach or to request scope extensions. Additionally, external factors – such as market factors, changes in business strategy, and new technology opportunities – may open up opportunities to extend and refine the architecture.
In these circumstances, a Change Request may be submitted in order to kick-start a further cycle of architecture work
upvoted 1 times
...
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
rockyslav
2 years, 1 month agorockyslav
2 years, 1 month agojunkz
2 years, 1 month ago