Question #: 59
Topic #: 1
[All OG0-091 Questions]

In Phase G, What document establishes the connection between the architecture organization and the implementation organization?

  • A. Architecture Contract
  • B. Architecture Landscape
  • C. Architecture Roadmap
  • D. Requirements Impact Statement
  • E. Transition Architecture
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
rockyslav
2 years, 1 month ago
Architecture Contracts are the joint agreements between development partners and sponsors on the deliverables, quality, and fitness-for-purpose of an architecture. Successful implementation of these agreements will be delivered through effective Architecture Governance. At the beginning of Phase G (Implementation Governance), between the architecture function and the function responsible for implementing the Enterprise Architecture defined in the preceding ADM phases.
upvoted 2 times
...
cbgrape
2 years, 3 months ago
14.5 Phase G establishes the connection between architecture and implementation organization, through the Architecture Contract.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...