Scenario -
Please read this scenario prior to answering the Question
You are serving as the Lead Architect for an Enterprise Architecture project team within a multinational oil and gas corporation. It is organized into two major business groupings:
-Upstream operations which include exploration for crude oil and natural gas and operating the infrastructure necessary to deliver oil and gas to the market.
-Downstream operations which include the manufacturing, distribution and marketing activities for oil products and chemicals
Safety is a priority for the company, with the aim to ensure it causes zero harm to people and the environment. The company has to satisfy the regulatory requirements of each of the countries it operates in.
The downstream business generates a third of the company's profits worldwide and includes more than 30,000 petrol stations and various oil refineries. In some countries it also includes oil refining, a retail petrol station network, lubricants manufacture and marketing, industrial fuel and lubricants sales. The practice for the downstream business has been to operate locally, managed by local "operating companies".
The Governing Board is concerned about the risk posed by operating in this complex global environment with a large part of the downstream business represented by local operating companies. As a result, the Chief Executive Officer (CEO) has appointed a Chief Compliance Officer (CCO) to be responsible for overseeing and managing compliance issues for the corporation. The CCO reports directly to the CEO.
The CCO has approved the expenditure of resources to establish an Enterprise Architecture program, and has mandated the use of the TOGAF standard as the framework. He has requested to be informed about the status of downstream operations that could impact regulatory compliance. He also wants the corporate legal staff and auditors to analyze all proposed new downstream operations to ensure that they are within the legal guidelines for each country. In addition, the local operating companies should be able to see that the architecture is appropriate for their needs.
The architecture project team has worked with the sponsor to complete a detailed Request for Architecture Work providing the high level project description. As the project commences the next phase, the necessary approvals from corporate and line management have been received.
Refer to the Scenario -
You have been asked to recommend an approach that would enable the development of an architecture that addresses the needs of the Chief Compliance
Officer, legal staff, auditors and the local operating companies.
Based on the TOGAF standard, Version 9.2, which of the following is the best answer?

  • A. You recommend that a set of models be created for each project architecture that can be used to ensure that the system will be compliant with the local regulations. A formal review should be held with the stakeholders to verify that their concerns have been properly addressed by the models.
  • B. You recommend that an analysis of the stakeholders is undertaken, including development of a Stakeholder Map. This will allow the architects to define groups of stakeholders who have common concerns. The concerns and relevant viewpoints should be defined for each group of stakeholders, and recorded in the Architecture Vision document.
  • C. You recommend that the ArchiMate modeling language is used to create a set of models that can be applied uniformly across all architecture projects. Each architecture should then be defined based on this fixed set of models. All concerned parties can then examine the models to ensure that their needs have been addressed.
  • D. You recommend that a Communications Plan be created to address the powerful and influential stakeholders. This plan should include a report that summarizes the key features of the architecture with respect to each location and reflect the stakeholders' requirements. You will check with each stakeholder that their concerns are being addressed.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
SonyJ
1 year, 12 months ago
why there are two different answers?
upvoted 1 times
...
noureldin
2 years, 1 month ago
Selected Answer: B
Answer is B because of the Stakeholder Map, an essential item to deal with all the relevant stakeholders
upvoted 2 times
...
Banzaaai
2 years, 4 months ago
Selected Answer: B
of a Stakeholder Map
upvoted 1 times
...
supratip
2 years, 4 months ago
Selected Answer: B
Multiple stakeholder concerns is 'stakeholder map'
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...