Actual exam question from The Open Group's OG0-092
Question #: 42
Topic #: 1
[All OG0-092 Questions]

SureFlight Air Carrier has received approval for the acquisition of a regional carrier.
To integrate the new acquisition, a TOGAF based enterprise architecture program has been initiated. The CIO sponsors the activity supported by the Chief
Architect.
In Phase A within the initial iteration the CIO wants to ensure that the architecture activities are recognized among the various stakeholders of the enterprise.
You are a consultant supporting the Chief Architect that should explain how to identify and engage the stakeholders at this stage of the program.
Identify the best answer accordingly to the TOGAF 9 guidelines.
Choose one of the following answers

  • A. Using the business scenarios technique you would identify supporting and not supporting stakeholders. Then you would list the set of viewpoints that are addressing the stakeholder concerns and share these with them.
  • B. You first priority is to communicate with the regional carrier stakeholders developing a Communications Plan to share main features and discuss opportunities with them.
  • C. You conduct a pilot proof of concept during Phase A to demonstrate the technical feasibility to the stakeholders explaining the approach available from your preferred suppliers.
  • D. You identify all the main stakeholders on both the acquired carrier and the rest of the enterprise. Using a stakeholder map, you classify and record their power in relation to this activity. You then focus on implementing the relevant viewpoints that can address the concerns of every main stakeholder identified in the stakeholders map.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
aptoapto
1 year, 6 months ago
Answer D. Question asks to "explain how to identify and engage the stakeholders". 31.6.2 highlights the importance of Stakeholder Matrix and its relevance toward answering this question. Business Scenario option is second best answer.
upvoted 1 times
...
Watad
1 year, 8 months ago
Selected Answer: D
Answer is D
upvoted 1 times
...
ArekA
1 year, 8 months ago
Selected Answer: D
Business Scenario: The technique is used to help identify, understand, and document business needs, and thereby to derive the business requirements that the architecture development has to address. These business requirements are documented as a Business Scenario.
upvoted 1 times
...
rkustagi
2 years, 6 months ago
Selected Answer: D
stakeholder map is essential. The business scenario is optional Choice D is correct
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...