Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam OG0-093 All Questions

View all questions & answers for the OG0-093 exam

Exam OG0-093 topic 1 question 202 discussion

Actual exam question from The Open Group's OG0-093
Question #: 202
Topic #: 1
[All OG0-093 Questions]

Scenario:
Please read this scenario prior to answering the question
The ABC company specializes in the development of wind turbine blades for use in large-scale commercial wind energy production systems. The company has manufacturing facilities located in Palm Springs, California, Omaha, Nebraska, and Winnipeg, Manitoba. Each of these plants supplies a different manufacturer that builds and sells complete systems. The turbine blades are custom engineered to meet each manufacturer's design specifications.
Until recently, most turbine blades were fabricated manually using molded fiber-reinforced plastics. However, recent improvements in composite materials, coupled with enhanced automated methods for precision application of materials during the molding process, have led to significant reduction in weight, increase in strength, and greatly improved blade longevity. The company has pioneered the development of a proprietary automated process for continuous extrusion of the turbine blades. Patents have been filed to protect the process, but certain trade secrets must be closely guarded.
The company has a mature Enterprise Architecture organization that is supported by a cross-functional Architecture Review Board. The Chief Information Officer and the Chief Operating Officer co-sponsor the Enterprise Architecture program.
The company has used T0GAF and its Architecture Development Method (ADM) to develop its automated manufacturing processes and systems that are used to design, manufacture, and test the blade assemblies. They have adapted their Enterprise Architecture to closely follow the TOGAF 9 framework. All of the company's enterprise architects have been trained and certified on TOGAF 9. Recently, an architecture project was completed that defined a standard approach for controlling the Automated Test System that is used at each plant to perform final quality assurance tests on each completed blade assembly. The
Manufacturing Architecture Board approved the plan for immediate implementation at each plant.
An Architecture Contract was developed that detailed the work needed to implement and deploy the new Automated Test System controller. The Chief Engineer, sponsor of the activity, has expressed concern that a uniform process be employed at each site to ensure consistency.

Refer to the Scenario -
You are the Lead Architect for this activity.
You have been asked to recommend the best approach to adopt to address the Chief Engineer's concern.
Based on TOGAF 9, which of the following is the best answer?

  • A. You create an Architecture Contract to manage and govern the implementation and migration process. If the contract is issued to an external party, you ensure that it is a fully enforceable legal contract. For internal development projects, you decide it is adequate to utilize a memorandum of understanding between the Manufacturing Architecture Board and the implementation organization. You recommend that if a deviation from the contract is detected, the Manufacturing Architecture Board should modify the Architecture Contract to allow the implementation organization the ability to customize the process to meet their local needs. As a result, you then issue a new Request for Architecture Work to implement the modified Architecture Definition.
  • B. You create an Architecture Contract to manage and govern the implementation and migration process. If the contract is issued to an external party, you ensure that it is a fully enforceable legal contract. For internal development projects, you decide it is adequate to utilize a memorandum of understanding between the Manufacturing Architecture Board and the implementation organization. You recommend that if a deviation from the Architecture Contract is detected, the Manufacturing Architecture Board grant a dispensation ID allow the implementation organization the ability to customize the process to meet their local needs.
  • C. You create an Architecture Contract to manage and govern the implementation and migration process. If the contract is issued to an external party, you ensure that it is a fully enforceable legal contract. For internal development projects, you decide it is adequate to utilize a memorandum of understanding between the Manufacturing Architecture Board and the implementation organization. You ensure that the Manufacturing Architecture Board reviews all deviations from the Architecture Contract, and considers whether or not to grant a dispensation to allow the implementation organization to customize the process to meet their local needs.
  • D. You create an Architecture Contract to govern the implementation and migration process at each site. If the contract is issued to an external party, you ensure that it is a fully enforceable legal contract. You ensure that the contract addresses the project objectives, effectiveness metrics, acceptance criteria, and risk management. You then schedule compliance reviews at key points in the implementation process to ensure that the work is proceeding in accordance with the Architecture Definition. Based on the results, you ensure that the Manufacturing Architecture Board reviews all deviations from the Architecture Contract, and considers whether or not to grant a dispensation to allow the implementation organization to customize the process to meet their local needs.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
OCHT
1 year, 3 months ago
Selected Answer: D
**Keyword Combination:** - **"Contract-Governance-Compliance-Dispensation"** **Explanation:** - **Contract:** Creating an Architecture Contract to govern the process, ensuring legal enforceability. - **Governance:** Addressing project objectives, metrics, acceptance criteria, and risk management within the contract. - **Compliance:** Scheduling reviews at key points to ensure alignment with the Architecture Definition. - **Dispensation:** Allowing the Manufacturing Architecture Board to review deviations and consider granting customization to meet local needs. This combination encapsulates the core principles of the chosen approach, emphasizing the contract's role in governance, the importance of compliance checks, and the potential for dispensation to customize the process. It's designed to be more memorable and practical for your needs.
upvoted 2 times
...
OCHT
1 year, 7 months ago
Selected Answer: D
Section 22.3.3: Architecture Contracts (for information on contracts and their significance) (https://pubs.opengroup.org/architecture/togaf91-doc/arch/chap22.html#tag_22_03_03) Section 43.4: Implementing Governance (for information on governance, compliance reviews, and the role of the Architecture Board) (https://pubs.opengroup.org/architecture/togaf91-doc/arch/chap43.html#tag_43_04) The hints/keywords from the question that should lead to option D are: Chief Engineer's concern about a uniform process at each site Ensuring consistency Addressing project objectives, effectiveness metrics, acceptance criteria, and risk management Involvement of the Manufacturing Architecture Board Compliance reviews
upvoted 1 times
...
KrishnaKM
1 year, 8 months ago
Selected Answer: C
C seems to be correct.
upvoted 1 times
...
noureldin
2 years ago
Selected Answer: D
Must be "manage and govern" not just govern b/c https://pubs.opengroup.org/architecture/togaf8-doc/arch/chap25.html which says "This contract is also used to manage changes to the enterprise architecture in Phase H." Additionally, chief engineer says wants uniform deployment, which eliminates A & B b/c board needs to approve those.
upvoted 1 times
...
noureldin
2 years ago
Selected Answer: D
Though D appears to be right, i think C is correct. The reason I think is, they have mentioned that the process should be uniform. The only difference in C and D is D says the process at each site where as C does not say that. C too talks about reviews for deviations so the concerns are addressed.
upvoted 2 times
...
MrCee1
2 years, 1 month ago
Selected Answer: D
It's D
upvoted 1 times
...
PrashanttheCloudMaster
2 years, 7 months ago
Correct Answer best ---> worst D C B A
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...