In which ADM phase is the Implementation and Migration Plan coordinated with other activities in the enterprise?

  • A. Phase A
  • B. Phase G
  • C. Phase E
  • D. Phase H
  • E. Phase F
Show Suggested Answer Hide Answer
Suggested Answer: E 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
noureldin
2 years, 1 month ago
Selected Answer: E
13.1 Objectives Ensure that the Implementation and Migration Plan is co-ordinated with the enterprise's approach to managing and implementing change in the enterprise's overall change portfolio https://pubs.opengroup.org/architecture/togaf9-doc/arch/chap13.html
upvoted 3 times
...
PrashanttheCloudMaster
2 years, 7 months ago
Correct Answer 3.1 Objectives The objectives of Phase F are to: Finalize the Architecture Roadmap and the supporting Implementation and Migration Plan Ensure that the Implementation and Migration Plan is co-ordinated with the enterprise's approach to managing and implementing change in the enterprise's overall change portfolio Ensure that the business value and cost of work packages and Transition Architectures is understood by key stakeholders
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...