Exam OG0-093 topic 1 question 307 discussion

Actual exam question from The Open Group's OG0-093
Question #: 307
Topic #: 1
[All OG0-093 Questions]

Which phase of the TOGAF ADM is the first phase directly concerned with the planning for the implementation of the target architecture(s)?

  • A. Phase D
  • B. Phase E
  • C. Phase F
  • D. Phase G
  • E. Phase H
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
evangelist
1 month, 1 week ago
Selected Answer: B
Phase E is the first phase in TOGAF ADM that directly focuses on implementation planning. It: Identifies major implementation projects Groups them into transition architectures Evaluates implementation resources and constraints Develops an overall implementation and migration strategy Prior phases (A-D) focus on architecture development, while subsequent phases (F-H) handle detailed migration planning, governance, and change management.
upvoted 1 times
...
noureldin
4 months ago
Selected Answer: B
13.2 Approach Phase E is the first phase which is directly concerned with the structure of how the Target Architecture will be implemented. https://pubs.opengroup.org/architecture/togaf90-doc/arch/chap13.html
upvoted 2 times
...
PrashanttheCloudMaster
9 months, 3 weeks ago
Correct Answer 12.5 Approach Phase E concentrates on how to deliver the architecture. It takes into account the complete set of gaps between the Target and Baseline Architectures in all architecture domains, and logically groups changes into work packages within the enterprise's portfolios. This is an effort to build a best-fit roadmap that is based upon the stakeholder requirements, the enterprise's business transformation readiness, identified opportunities and solutions, and identified implementation constraints. The key is to focus on the final target while realizing incremental business value. Phase E is the initial step on the creation of the Implementation and Migration Plan which is completed in Phase F. It provides the basis of a well considered Implementation and Migration Plan that is integrated into the enterprise's portfolio in Phase F.
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...