Complete the sentence. In a gap analysis, a building block that appears in the Target Architecture but does not appear in the Baseline Architecture indicates
_____

  • A. nonconformant solution building blocks
  • B. an error has occurred and the architecture must be re-evaluated
  • C. requirements have not been properly documented
  • D. functionality that should be eliminated
  • E. a new function that must be built or procured
Show Suggested Answer Hide Answer
Suggested Answer: E 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
noureldin
2 years, 1 month ago
Selected Answer: E
27.2 Suggested Steps Where an ABB from the Baseline Architecture is missing in the Target Architecture, each must be reviewed. If it was correctly eliminated, mark it as such in the appropriate "Eliminated" cell. If it was not, an accidental omission in the Target Architecture has been uncovered that must be addressed by reinstating the ABB in the next iteration of the architecture design - mark it as such in the appropriate "Eliminated" cell. Where an ABB from the Target Architecture cannot be found in the Baseline Architecture, mark it at the intersection with the "New" row as a gap that needs to filled, either by developing or procuring the building block. When the exercise is complete, anything under "Eliminated" or "New" is a gap, which should either be explained as correctly eliminated, or marked as to be addressed by reinstating or developing/procuring the function. https://pubs.opengroup.org/architecture/togaf91-doc/m/chap27.html
upvoted 2 times
...
PrashanttheCloudMaster
2 years, 7 months ago
Correct Answer 23.2 Suggested Steps Where an ABB from the Target Architecture cannot be found in the Baseline Architecture, mark it at the intersection with the "New" row as a gap that needs to filled, either by developing or procuring the building block When the exercise is complete, anything under "Eliminated" or "New" is a gap, which should either be explained as correctly eliminated, or marked as to be addressed by reinstating or developing/procuring the function.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...