Question #: 108
Topic #: 1
[All OG0-093 Questions]

Complete the sentence. The TOGAF risk categorization after the implementation of mitigating actions is known as the level of risk.

  • A. Critical
  • B. Initial
  • C. Intermediate
  • D. Residual
  • E. Unmitigated
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
noureldin
2 years ago
Selected Answer: D
27.1 Introduction There are two levels of risk that should be considered, namely: Initial Level of Risk: risk categorization prior to determining and implementing mitigating actions Residual Level of Risk: risk categorization after implementation of mitigating actions (if any) https://pubs.opengroup.org/architecture/togaf9-doc/arch/chap27.html
upvoted 4 times
...
PrashanttheCloudMaster
2 years, 7 months ago
Correct Answer
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...