In Phase H it is critical that the governance body establish criter ia to judge whether a Change
Request warrants just an architecture update or whether it warrants starting a new cycle of the
ADM. It is especially important to avoid "creeping elegance", and the governance body must
continue to look for changes that relate directly to business value.
An Architecture Compliance report should state whether the change is compliant to the current
architecture. If it is non-compliant, an exemption may be granted with valid rationale. If the
change has high impact on the architecture, then a strategy to manage its impact should be
defined.
32.2.11 Change Request
Purpose
During implementation of an architecture, as more facts become known, it is possible that the original Architecture Definition and requirements are not suitable or are not sufficient to complete the implementation of a solution. In these circumstances, it is necessary for implementation projects to either deviate from the suggested architectural approach or to request scope extensions. Additionally, external factors - such as market factors, changes in business strategy, and new technology opportunities - may open up opportunities to extend and refine the architecture.
In these circumstances, a Change Request may be submitted in order to kick-start a further cycle of architecture work.
https://pubs.opengroup.org/architecture/togaf9-doc/arch/chap32.html
Correct Answer
32.2.11 Change Request
Purpose
During implementation of an architecture, as more facts become known, it is possible that the original Architecture Definition and requirements are not suitable or are not sufficient to complete the implementation of a solution. In these circumstances, it is necessary for implementation projects to either deviate from the suggested architectural approach or to request scope extensions. Additionally, external factors - such as market factors, changes in business strategy, and new technology opportunities - may open up opportunities to extend and refine the architecture.
In these circumstances, a Change Request may be submitted in order to kick-start a further cycle of architecture work.
upvoted 1 times
...
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
ZK000001qws
1 year, 3 months agonoureldin
2 years agoBanzaaai
2 years, 5 months agoPrashanttheCloudMaster
2 years, 7 months ago