The technique known as gap analysis is widely used in the TOGAF Architecture Development Method (ADM) to validate an architecture that is being developed. The basic premise is to highlight a shortfall between the Baseline Architecture and the Target Architecture; that is, items that have been deliberately omitted, accidentally left out, or not yet defined.
https://pubs.opengroup.org/architecture/togaf91-doc/m/chap27.html
Correct Answer - C. It highlights services that are yet to be developed
https://pubs.opengroup.org/architecture/togaf9-doc/arch/chap23.html#tag_23_01
upvoted 1 times
...
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
noureldin
2 years, 1 month agoPrashanttheCloudMaster
2 years, 7 months ago