Question #: 7
Topic #: 1
[All OG0-093 Questions]

According to TOGAF, when creating views for a particular architecture, what is the recommended first step?

  • A. Design a viewpoint to address all stakeholder concerns
  • B. Develop views for the target architecture first
  • C. Ensure completeness of the architecture
  • D. Refer to existing libraries of viewpoints, to identify one for re-use
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Gurt
10 months, 2 weeks ago
ISO/IEC/IEEE 42010:2011 itself does not require any specific process for developing architecture viewpoints or creating views from them. Where ISO/IEC/IEEE 42010:2011 has been adopted and become well-established practice within an organization, it will often be possible to create the required views for a particular architecture by following these steps: Refer to an existing library of architecture viewpoints
upvoted 1 times
...
noureldin
2 years, 1 month ago
Selected Answer: D
31.2.2 Architecture View Creation Process steps: 1. Refer to an existing library of architecture viewpoints 2. Select the appropriate architecture viewpoints (based on the stakeholders and concerns that need to be covered by views) 3. Generate views of the system by using the selected architecture viewpoints as templates https://pubs.opengroup.org/architecture/togaf9-doc/arch/chap31.html
upvoted 1 times
...
KASPoint
2 years, 6 months ago
Selected Answer: D
31.2.2 Architecture View Creation Process As mentioned above, the TOGAF framework encourages but does not mandate the use of ISO/IEC/IEEE 42010: 2011. The following description therefore covers both the situation where ISO/IEC/IEEE 42010: 2011 has been adopted and where it has not. ISO/IEC/IEEE 42010: 2011 itself does not require any specific process for developing architecture viewpoints or creating views from them. Where ISO/IEC/IEEE 42010: 2011 has been adopted and become well-established practice within an organization, it will often be possible to create the required views for a particular architecture by following these steps: 1. Refer to an existing library of architecture viewpoints 2. Select the appropriate architecture viewpoints (based on the stakeholders and concerns that need to be covered by views) 3. Generate views of the system by using the selected architecture viewpoints as templates
upvoted 1 times
...
PrashanttheCloudMaster
2 years, 7 months ago
Correct Answer .. Seems from TOGAF8
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...