The steps in Phase F are as follows:
■ Confirm management framework interactions for Implementation and Migration Plan (seeSection 13.3.1)
■ Assign a business value to each work package (see Section 13.3.2)
■ Estimate resource requirements, project timings, and availability/delivery vehicle (see
Section 13.3.3)
■ Prioritize the migration projects through the conduct of a cost/benefit assessment and risk validation (see Section 13.3.4)
■ Confirm Architecture Roadmap and update Architecture Definition Document (see Section 13.3.5)
■ Complete the Implementation and Migration Plan (see Section 13.3.6)
■ Complete the architecture development cycle and document lessons learned (see Section 13.3.7)
Development of the Implementation and Migration Plan
The outline Implementation and Migration Plan is created in Phase E and then finalized in Phase F.
The objectives of Phase F are to:
■ Finalize the Architecture Roadmap and the supporting Implementation and Migration
Plan.
■ Ensure that the Implementation and Migration Plan is co-ordinated with the enterprise’s
approach to managing and implementing change in the enterprise’s overall change
portfolio.
■ Ensure that the business value and cost of work packages and Transition Architectures is understood by key stakeholders.
The is answer D:
https://pubs.opengroup.org/architecture/togaf9-doc/arch/
Ensure that the Implementation and Migration Plan is co-ordinated with the enterprise's approach to managing and implementing change in the enterprise's overall change portfolio.
upvoted 2 times
...
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
rockyslav
2 years, 1 month agorockyslav
2 years, 1 month agoThe1stSeeker
3 years, 4 months ago