Which of the following describes an objective of Phase F: Migration Planning Phase?

  • A. Develop a Target Technology Architecture
  • B. Consolidate the Gap Analysis results from Phases B through D
  • C. Generate and gain consensus on an initial Architecture Roadmap
  • D. Coordinate the Implementation and Migration Plan with other frameworks
  • E. Operate the governance framework and manage an architecture contract
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
rockyslav
2 years, 1 month ago
The steps in Phase F are as follows: ■ Confirm management framework interactions for Implementation and Migration Plan (seeSection 13.3.1) ■ Assign a business value to each work package (see Section 13.3.2) ■ Estimate resource requirements, project timings, and availability/delivery vehicle (see Section 13.3.3) ■ Prioritize the migration projects through the conduct of a cost/benefit assessment and risk validation (see Section 13.3.4) ■ Confirm Architecture Roadmap and update Architecture Definition Document (see Section 13.3.5) ■ Complete the Implementation and Migration Plan (see Section 13.3.6) ■ Complete the architecture development cycle and document lessons learned (see Section 13.3.7)
upvoted 1 times
...
rockyslav
2 years, 1 month ago
Development of the Implementation and Migration Plan The outline Implementation and Migration Plan is created in Phase E and then finalized in Phase F. The objectives of Phase F are to: ■ Finalize the Architecture Roadmap and the supporting Implementation and Migration Plan. ■ Ensure that the Implementation and Migration Plan is co-ordinated with the enterprise’s approach to managing and implementing change in the enterprise’s overall change portfolio. ■ Ensure that the business value and cost of work packages and Transition Architectures is understood by key stakeholders.
upvoted 1 times
...
The1stSeeker
3 years, 4 months ago
The is answer D: https://pubs.opengroup.org/architecture/togaf9-doc/arch/ Ensure that the Implementation and Migration Plan is co-ordinated with the enterprise's approach to managing and implementing change in the enterprise's overall change portfolio.
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...