Yes. Answer B - Phase F
13.5 Approach
The focus of Phase F is the creation of an Implementation and Migration Plan in co-operation with the project and portfolio managers.
Phase E provides an incomplete Architecture Roadmap and Implementation and Migration Plan that address the Statement of Architecture Work. In Phase F this Roadmap and the Implementation and Migration Plan are integrated with the enterprise's other change activity.
This is wrong. This is initially created in phase E then finalised in F. 12.3.11 Create the Architecture Roadmap & Implementation and Migration Plan
upvoted 2 times
...
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
rockyslav
2 years, 1 month agosc597
2 years, 6 months agosameersoftyhcl
3 years, 5 months agoTOM1000
3 years, 6 months ago