Question #: 37
Topic #: 1
[All OG0-093 Questions]

Complete the sentence. A gap analysis will enable the architect to do all of the following except _____.

  • A. identify building blocks that have been inadvertently omitted
  • B. identify building blocks that have been intentionally eliminated
  • C. identify building blocks to be carried over
  • D. identify new building blocks that are needed
  • E. identify potential vendors to provide new building blocks
Show Suggested Answer Hide Answer
Suggested Answer: E 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
noureldin
2 years, 1 month ago
Selected Answer: E
Activities Key activities in this step include: Create gap matrix as described under Approach, above. Identify building blocks to be carried over, classifying as either changed or unchanged. Identify eliminated building blocks. Identify new building blocks. Identify gaps and classify as those that should be developed, those that should be procured, and those inherited. https://pubs.opengroup.org/architecture/togaf80-doc/arch/p2/ta/ta_gapan.htm
upvoted 2 times
...
PrashanttheCloudMaster
2 years, 7 months ago
Correct Answer Check Chapter 23.2 Suggested Steps(TOGAF9.2)
upvoted 1 times
...
harofe2121
2 years, 8 months ago
Selected Answer: E
https://pubs.opengroup.org/architecture/togaf91-doc/arch/chap27.html Talks about all but there is no reference of vendor on this page
upvoted 1 times
...
ankit89
3 years, 1 month ago
Ans: B The technique known as gap analysis is widely used in the TOGAF Architecture Development Method (ADM) to validate an architecture that is being developed. The basic premise is to highlight a shortfall between the Baseline Architecture and the Target Architecture; that is, items that have been deliberately omitted, accidentally left out, or not yet defined. deliberately omitted!!
upvoted 2 times
...
sushmapatil
3 years, 9 months ago
Since Gap Ananlysis doesn't talk about vendors or stakeholders.
upvoted 3 times
...
Satish_Pappu
3 years, 10 months ago
All the options seem to be right here, I am not sure why E was chosen as the Answer.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...