Correct Answer D:
There are two levels of risk that should be considered, namely:
Initial Level of Risk: risk categorization prior to determining and implementing mitigating actions
Residual Level of Risk: risk categorization after implementation of mitigating actions (if any)
27. Risk Management
27.1 Introduction
There are two levels of risk that should be considered, namely:
Initial Level of Risk: risk categorization prior to determining and implementing mitigating actions
Residual Level of Risk: risk categorization after implementation of mitigating actions (if any)
27.1 Introduction
There are two levels of risk that should be considered, namely:
Initial Level of Risk: risk categorization prior to determining and implementing mitigating actions
Residual Level of Risk: risk categorization after implementation of mitigating actions (if any)
https://pubs.opengroup.org/architecture/togaf9-doc/arch/chap27.html#:~:text=Initial%20Level%20of%20Risk%3A%20risk,of%20mitigating%20actions%20(if%20any)
Correct Answer
There are two levels of risk that should be considered, namely:
Initial Level of Risk: risk categorization prior to determining and implementing mitigating actions
Residual Level of Risk: risk categorization after implementation of mitigating actions (if any)
upvoted 1 times
...
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
RVR
Highly Voted 3 years, 11 months agofais
Most Recent 1 year, 5 months agoLillianXUE
1 year, 5 months agonoureldin
2 years, 1 month agoPrashanttheCloudMaster
2 years, 7 months ago