Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam OG0-093 All Questions

View all questions & answers for the OG0-093 exam

Exam OG0-093 topic 1 question 18 discussion

Actual exam question from The Open Group's OG0-093
Question #: 18
Topic #: 1
[All OG0-093 Questions]

In which phase of the TOGAF ADM are Gap Analysis results from earlier phases consolidated?

  • A. Phase D
  • B. Phase E
  • C. Phase F
  • D. Phase G
  • E. Phase H
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
noureldin
2 years, 1 month ago
Selected Answer: B
13.1 Objectives The objectives of Phase E are to: Generate the initial complete version of the Architecture Roadmap, based upon the gap analysis and candidate Architecture Roadmap components from Phases B, C, and D --- The steps in Phase E are as follows: . . . • 13.4.3 Review and Consolidate Gap Analysis Results from Phases B to D •. . . --- 13.4.3 Review and Consolidate Gap Analysis Results from Phases B to D Consolidate and integrate the gap analysis results from the Business, Information Systems, and Technology Architectures (created in Phases B to D) https://pubs.opengroup.org/architecture/togaf91-doc/arch/chap13.html
upvoted 1 times
...
PrashanttheCloudMaster
2 years, 7 months ago
Correct Answer 12.3.3 Review and Consolidate Gap Analysis Results from Phases B to D Consolidate and integrate the gap analysis results from the Business, Information Systems, and Technology Architectures (created in Phases B to D) and assess their implications with respect to potential solutions and inter-dependencies. This should be done by creating a Consolidated Gaps, Solutions, and Dependencies matrix, as shown in Part III, 24.2 Consolidated Gaps, Solutions, & Dependencies Matrix , which will enable the identification of Solution Building Blocks (SBBs) that could potentially address one or more gaps and their associated ABBs. Review the Phase B, C, and D gap analysis results and consolidate them in a single list. The gaps should be consolidated along with potential solutions to the gaps and dependencies. A recommended technique for determining the dependencies is to use sets of views such as the Business Interaction matrix, the Data Entity/Business Function matrix, and the Application/Function matrix to completely relate elements from different architectural domains
upvoted 1 times
...
BMill
3 years, 3 months ago
one of the objectives of Phase E are to: Generate the initial complete version of the Architecture Roadmap, based upon the gap analysis and candidate Architecture Roadmap components from Phases B, C, and D
upvoted 1 times
...
PaulM0000
4 years ago
Surely this should be Phase E?
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...