Scenario:
Please read this scenario prior to answering the question
Your role is that of a consultant to the Lead Enterprise Architect in a company that speicializes in luxury electric cars and their powertrain components, and also produces battery-charging equipment. It has its own distribution network, its own showrooms, and sells directly to customers via the internet. The company has four manufacturing facilities, two in the North America, one in Europe, and one in Asia.
A challenge that the company is facing to scale up the number of vehicles coming off the production line to meed customer demand, while maintaining quality. At the moment there are supply chain storages for key electronic components related to the autonomous drive system. In response the this, the research arm of the company has pioneered the development of a new self-driving platform. This new design uses common off-the-shelf components that will allow for a significant increase in overall vehicle production. This new design is ready to go into production.
The company has a mature Enterprise Architecture practice that is supported by a cross-functional Architecture Board. The TOGAF standard is used for developing the automated manufacturing process and systems used to design, manufacture and test the new design. The Chief Information Officer and the Chief
Operating Officer co-sponsor the Enterprise Architecture program.
As part of putting the new self-driving platform into production, adjustments to the automated assembly processes need to be made. A pilot architecture project at a single location has defined an updated approach for controlling the automated test systems used to perform final quality assurance. The Chief Engineer, sponsor of the activity, and the Architecture Board have approved the plan for immediate implementation at each plant.
Architecture Contracts have been developed that detail the work needed to implement and deploy the new automated test system controller for each location. The
Chief Engineer has expressed concern that a uniform process be employed at each location to ensure consistency and quality.

Refer to the Scenario -
The Lead Enterprise Architect has asked you to recommend the best approach to address the Chief Engineer's concern.
Based on the TOGAF standard, which of the following is the best answer?

  • A. You create an Architecture Contract to manage and govern the implementation and migration process. If the contract is issued to an external party, you ensure that it is a fully enforceable legal contract. For internal development projects, you decide it is adequate to utilize a memorandum of understanding between the Architecture Board and the implementation organization. You recommend that if a deviation from the Architecture Contract is detected, the Architecture Board grant a dispensation to allow the implementation organization the ability to customize the process to meet their local needs.
  • B. You use the Architecture Contracts to manage the architecture governance processes for the project across the locations. You deploy monitoring tools to assess the performance of each completed drive assembly at each location and develop change requirements if necessary. You recommend that if a deviation from the contract is detected, the Architecture Board should modify the Architecture Contract to allow the implementation organization the ability to customize the process to meet their local needs. As a result, you then issue a new Request for Architecture Work to implement the modified Architecture Definition.
  • C. You create an Architecture Contract to manage and govern the implementation and migration process at each location. For internal development projects, you issue a memorandum of understanding between the Architecture Board and the implementation organization. For contracts issued to an external party, you ensure that it is a fully enforceable legal contract. You ensure that the Architecture Board reviews all deviations from the Architecture Contract, and considers whether or not to grant a dispensation to allow the implementation organization to customize the process to meet their local needs.
  • D. You review the applicable Architecture Contract for each location, ensuring that it addresses the project objectives, effectiveness metrics, acceptance criteria, and risk management. In cases where the contract is issued to an external party, you ensure that it is a legally enforceable contract. You schedule compliance reviews at key points in the implementation process to ensure that the work is proceeding in accordance with the Architecture Definition. You ensure that the Architecture Board reviews all deviations from the Architecture Contract, and considers whether or not to grant a dispensation to allow the implementation organization to customize the process to meet their local needs.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
ppoulop
Highly Voted 3 years, 11 months ago
D seems the correct one to me
upvoted 7 times
...
OCHT
Most Recent 1 year, 3 months ago
Selected Answer: D
Given the Chief Engineer's concern for a uniform process to ensure consistency and quality, Option D seems the best fit. It ensures that the Architecture Contract addresses the project objectives, includes compliance reviews at key points, and allows for potential customization if needed, all of which aligns with the need for a uniform process across all locations.
upvoted 2 times
...
noureldin
2 years, 1 month ago
Selected Answer: D
Why memorandum of understanding is important to answer or choose C, it is not even TOGAF term, the contract is the memorandum of understanding. I would say D
upvoted 1 times
...
NicWorth
2 years, 1 month ago
I would say B as the contract has already been developed. A and C are out as it states you create a Contract but that has already been done according to the question. D doesn't seem 100% right as it talks about external parties but the question does not refer to external parties...
upvoted 2 times
...
Banzaaai
2 years, 4 months ago
Selected Answer: D
You review the applicable Architecture Contract for each location
upvoted 1 times
...
nem
2 years, 5 months ago
Selected Answer: D
Agree with D as the best answer. The concern from the chief engineer is about consistency and quality. Since architecture contracts developed already, compliance review process is the TOGAF way
upvoted 1 times
...
youthanasia
3 years, 7 months ago
D is correct for me. The architecture contract is in place, so A & C are out, there is no need to create what is already created. For B, what has the performance of drive assembly have to do with with EA, surely this would be handled by the manufacturing team of the drive assembly. D is the only complete answer.
upvoted 3 times
...
bsi
3 years, 8 months ago
A should be fine. I was also mislead by anwers, but A is speaking about uniform contract (single). It does not talk about review for each location (like C or D), but only on one Contract covering a concern of uniformity B is talking about modifying a Contract, which should not happen.....
upvoted 3 times
...
venksfc
4 years, 1 month ago
C is correct to ensure to address concern that a uniform process be employed at each location to ensure consistency.
upvoted 1 times
...
jayecho
4 years, 1 month ago
should be C since it covers the relevant concerns
upvoted 3 times
...
gsneaks76
4 years, 2 months ago
Looks like B to me, contracts already exist and you need to monitor and be able to change if need be
upvoted 1 times
bsi
3 years, 8 months ago
I fully agree that contracts exists so we could discard A and C. But D looks more detailed than B. I would go for D.
upvoted 5 times
bsi
3 years, 8 months ago
I wrote it and upper comment ("I fully agree.... ") is wrong - please do not confirm this or previous comment :)
upvoted 1 times
...
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...