Which phase of the TOGAF ADM is the first phase directly concerned with the planning for the implementation of the target architecture(s)?

  • A. Phase D
  • B. Phase E
  • C. Phase F
  • D. Phase G
  • E. Phase H
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
coolala
Highly Voted 3 years ago
B Please refer to the Steps and Outputs of Phase E. The Implementation and Migration Plan is initiated in phase E and finalized in phase F.
upvoted 8 times
...
p7vpki7qz
Most Recent 8 months ago
Selected Answer: C
The first phase of the TOGAF Architecture Development Method (ADM) that is directly concerned with the planning for the implementation of the target architecture(s) is: Answer C, Phase F = Migration Planning This focuses on creating a detailed plan to move from the current architecture to the target architecture. This involves identifying and prioritizing projects, developing a detailed Implementation and Migration Plan, and preparing the organization for the changes. This phase is crucial for ensuring that the transition to the new architecture is feasible, cost-effective, and aligned with the organization's strategic objectives.
upvoted 1 times
...
sanbt
1 year, 10 months ago
Selected Answer: B
B Implementation and migration strategy is the output of Phase E
upvoted 2 times
...
Toldwin
3 years, 1 month ago
Should be phase F migration planning : https://pubs.opengroup.org/architecture/togaf9-doc/arch/chap13.html I see no specific planning in the Phase E description... Quote "Consolidate the work packages and Transition Architectures into the Architecture Roadmap, Version 0.1, which describes a timeline of the progression from the Baseline Architecture to the Target Architecture. The timeline informs the Implementation and Migration Plan. The Architecture Roadmap frames the migration planning in Phase F. Identified Transition Architectures and work packages should have a clear set of outcomes. The Architecture Roadmap must demonstrate how the selection and timeline of Transition Architectures and work packages realizes the Target Architecture."
upvoted 3 times
scuzzy2010
3 years ago
I agree.. "The Implementation and Migration Plan provides a schedule for implementation of the solution described by a Transition Architecture. The Implementation and Migration Plan includes timing, cost, resources, benefits, and milestones for the implementation."
upvoted 2 times
...
...
Geeloo
4 years, 2 months ago
Answer is B
upvoted 4 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...