Exam OG0-093 topic 1 question 214 discussion

Actual exam question from The Open Group's OG0-093
Question #: 214
Topic #: 1
[All OG0-093 Questions]

Scenario:
Please read this scenario prior to answering the question
Your role is that of a consultant to the Lead Enterprise Architect in a company that develops wind turbines for use in wind farms. The company has three manufacturing facilities, one in North America, one in Asia, and one in Europe. Each of these facilities supplies the power industry in its region.
The company recognizes that the long-term technical potential of wind energy can address the current global dependency on carbon fuels. In order to do so this will require wind turbines to be installed over large areas of higher wind resources. In particular offshore wind farms can contribute substantially more energy than land stationed turbines.
The research arm of the company has pioneered the development of an offshore wind turbine design, with an improved turbine blade and power system, that will produce up to 20% more energy. This will allow the production of significantly more saleable energy. This new design is ready to go into production.
The company has a mature Enterprise Architecture practice supported by a cross-functional Architecture Board and uses the TOGAF standard. The Chief
Information Officer and the Chief Operating Officer co-sponsor the Enterprise Architecture program.
As part of putting the new design into production, a pilot architecture project has defined an updated standard approach for controlling the automated test systems used to perform final quality assurance to perform final quality assurance. The Architecture Board approved the plan for immediate implementation at each plant.
Architecture Contracts have been developed that detail the work needed to implement and deploy the new Automated Test System controller for each location.
The Chief Engineer, sponsor of the activity, has expressed concern that a uniform process be employed at each location to ensure consistency.

Refer to the Scenario -
You have been asked to recommend the best approach to address the Chief Engineer's concern.
Based on the TOGAF standard, Version 9.2, which of the following is the best answer?

  • A. You review the applicable Architecture Contract for each location, ensuring that it addresses the project objectives, effectiveness metrics, acceptance criteria, and risk management. In cases where the contract is issued to an external party, you ensure that it is a legally enforceable contract. You schedule compliance reviews at key points in the implementation process to ensure that the work is proceeding in accordance with the Architecture Definition. You ensure that the Architecture Board reviews all deviations from the Architecture Contract, and considers whether or not to grant a dispensation to allow the implementation organization to customize the process to meet their local needs.
  • B. You create an Architecture Contract to manage and govern the implementation and migration process at each location. For internal development projects, you issue a memorandum of understanding between the Architecture Board and the implementation organization. For contracts issued to an external party, you ensure that it is a fully enforceable legal contract. You ensure that the Architecture Board reviews all deviations from the Architecture Contract, and considers whether or not to grant a dispensation to allow the implementation organization to customize the process to meet their local needs.
  • C. You create an Architecture Contract to manage and govern the implementation and migration process. If the contract is issued to an external party, you ensure that it is a fully enforceable legal contract. For internal development projects, you decide it is adequate to utilize a memorandum of understanding between the Architecture Board and the implementation organization. You recommend that if a deviation from the Architecture Contract is detected, the Architecture Board grant a dispensation to allow the implementation organization the ability to customize the process to meet their local needs.
  • D. You use the Architecture Contracts to manage the architecture governance processes for the project across the locations. You deploy monitoring tools to assess the performance of each completed turbine at each location and develop change requirements if necessary. You recommend that if a deviation from the contract is detected, the Architecture Board should modify the Architecture Contract to allow the implementation organization the ability to customize the process to meet their local needs. As a result, you then issue a new Request for Architecture Work to implement the modified Architecture Definition.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
venksfc
Highly Voted 4 years, 1 month ago
Correct answer is A; The section in D goes against the requirement: to allow the implementation organization the ability to customize the process to meet their local needs
upvoted 12 times
lepperboy
1 year, 3 months ago
yes agree - key point here is making sure the process is uniform across each location - this was a key concern.
upvoted 1 times
...
...
Dmitry777
Most Recent 10 months, 2 weeks ago
Selected Answer: A
A is the correct answer
upvoted 1 times
...
PratsMic
1 year, 5 months ago
ALL THE BS WRONG ANSWERS ON EXAM TOPICS https://www.examtopics.com/discussions/the-open-group/view/31323-exam-og0-092-topic-1-question-17-discussion/
upvoted 3 times
...
Rjessaye
1 year, 6 months ago
Selected Answer: D
I think the arch contract is already created and we have to just use it for governance
upvoted 1 times
...
Elisa2021
1 year, 10 months ago
Answer A is more appropriate with approach in Phase H
upvoted 1 times
...
noureldin
1 year, 12 months ago
Selected Answer: A
As a consultant to lead architect, you cannot create an Architecture Contract…, you can only review. … At the same time.. Option A says “considers whether or not to grant a dispensation”.. whereas, option C directly says to provide dispensation which is not correct . Final Answer is Option A..
upvoted 2 times
...
MrCee1
2 years, 1 month ago
Selected Answer: A
A is the correct answer
upvoted 2 times
...
Banzaaai
2 years, 4 months ago
Selected Answer: A
A. You review the applicable Architecture Contract for each location, ensuring that it addresses the project objectives, effectiveness metrics, acceptance criteria, and risk management.
upvoted 2 times
...
diazed
2 years, 4 months ago
A is the correct Answer. Option B & C are irrelevant due to the arch contract is in place already. D option is a distractor.
upvoted 4 times
...
Nicholas_The_King_Kong
2 years, 8 months ago
I don't think it is possible that "D" is correct. It should be the king of all distractor here! How can the architecture contract be changed without scrutiny when one local implementation asked for it? And it is not the role of the EA to request for a new architecture work, isn't that the sponsor's role?
upvoted 1 times
...
sreejayan
2 years, 9 months ago
looks like A is the correct answer
upvoted 1 times
...
sreejayan
2 years, 9 months ago
A is the correct answer - need Board to approve to grant the change or not
upvoted 1 times
...
ankit89
3 years ago
A is correct
upvoted 1 times
...
youthanasia
3 years, 7 months ago
A is correct. The architecture contract is already developed, so, B & C are out. What does the performance of the turbines have to do with EA, nothing... So D is out.
upvoted 2 times
...
sushmapatil
3 years, 9 months ago
B seems to be corrects answer considering uniform & consistent process at each plant and dispensation decision.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...