Exam OG0-091 topic 1 question 16 discussion

Actual exam question from The Open Group's OG0-091
Question #: 16
Topic #: 1
[All OG0-091 Questions]

Which phase of the ADM is used to finalize a set of transition architectures that will support implementation?

  • A. Phase D
  • B. Phase E
  • C. Phase F
  • D. Phase G
  • E. Phase H
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
codezombie
Highly Voted 3 years, 3 months ago
Phase F Migration Planning- is the correct answer. One of the outputs of phase F is finalized transition architecture. In Phase E (Opportunities & solutions) your architecture roadmap is still draft which includes the transition architecture if any. They only get finalised in phase E.
upvoted 12 times
codezombie
3 years, 2 months ago
correction. They only get finalised in phase F.
upvoted 4 times
...
sroyc
2 years ago
Explanation is correct. Phase E for draft, Phase F for final.
upvoted 1 times
...
...
sanbt
Most Recent 1 year, 10 months ago
Selected Answer: C
Phase F addresses migration planning, that is, how to move from the Baseline to the Target Architectures by finalizing a detailed Implementation and Migration Plan.
upvoted 2 times
...
AnshMan
3 years, 4 months ago
Phase E: Opportunities and Solutions Phase E is the first phase concerned with implementation.
upvoted 1 times
AnshMan
3 years, 4 months ago
So answer should be "B. Phase E"
upvoted 2 times
...
...
CloudTrip
3 years, 8 months ago
Phase F is correct.
upvoted 2 times
...
CloudTrip
3 years, 9 months ago
Perform initial implementation planning and the identification of delivery vehicles for the building blocks identified in the previous phases. Determine whether an incremental approach is required, and if so identify Transition Architectures.
upvoted 1 times
...
CloudTrip
3 years, 9 months ago
Phase E: Opportunities & Solutions Perform initial implementation planning and the identification of delivery vehicles for the building blocks identified in the previous phases. Determine whether an increme
upvoted 1 times
...
mjdfreeiotcloud
3 years, 11 months ago
Phase C : limited to data and application Aspect
upvoted 1 times
...
mjdfreeiotcloud
3 years, 11 months ago
Phase F: implementtaion and migration Plan from Baseline to Target Architecture, that mean a set of architecture (helping implementation)
upvoted 2 times
...
cmcv
4 years, 3 months ago
Answer: C
upvoted 2 times
Kashmir2020
4 years ago
Phase F is Correct -Page 179 of book
upvoted 3 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...