What is an objective of the ADM Implementation Governance Phase?

  • A. To ensure conformance for the target architecture
  • B. To finalize the Implementation and Migration Plan
  • C. To provide continual monitoring of the governance framework
  • D. To establish the resources for architecture governance
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
klezlil
9 months, 1 week ago
Selected Answer: A
https://pubs.opengroup.org/togaf-standard/adm/chap11.html 11.1 Objectives The objectives of Phase G are to: Ensure conformance with the Target Architecture by implementation projects Perform appropriate Architecture Governance functions for the solution and any implementation-driven architecture Change Requests
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...