Question #: 35
Topic #: 1
[All OGEA-103 Questions]

What are the following activities part of?

Initial risk assessment -
Risk mitigation and residual risk assessment
Risk monitoring

  • A. Risk Management
  • B. Phase C
  • C. Phase A
  • D. Security Architecture
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
bmdibrahim
11 months, 2 weeks ago
Option A [VERIFIED] https://pubs.opengroup.org/architecture/togaf9-doc/arch/chap27.html
upvoted 1 times
...
CyanideX
11 months, 3 weeks ago
Selected Answer: A
A is correct
upvoted 1 times
...
thunderks
11 months, 3 weeks ago
Selected Answer: A
A is correct, they are all processes for risk management, reference https://pubs.opengroup.org/architecture/togaf9-doc/arch/chap27.html (introduction)
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...